By
DAVID HARRIS
If youre among the thousands of
commuters sitting in perpetual gridlock on the Van Wyck Expressway each morning, take
heart, Port Authority officials recently announced that they are on the fast track to
complete the AirTrain in record time.

High-traffic congestion is evident on the Van Wyck
Expwy. where construction has begun on the AirTrain project.
PRESS Photo By Ira Cohen
|
Since construction began on the
controversial project in the fall of 1999, those opposed to the plan have continually said
that three years is too long to keep the Expressway bottled up.
In an effort to speed up the construction
of the billion-dollar project, the Port Authority has formed a coalition with the
contractor, the Air Rail Transit Consortium (ARTC), to make building and design
simultaneous. In theory, engineers will now be able to more easily accommodate the needs
of the public in the planning and execution of the next leg of construction.
If it seems like those
concrete support columns are springing up along the median like wild onions, its
because they are. It takes about 17 hours to complete each one.

Workers erecting the AirTrain columns on the Van
Wyck Expwy. will be able to work faster following the information of the AirRail Transit
Consortium, officials said. (Inset) The AirTrain of the future.
PRESS Photo By Ira Cohen |
The first step is pile-driving, in
which eight to 10 steel girders are driven into the ground pneumatically. Next the girders
are topped with a concrete foundation. Inserted into that foundation is a vertical steel
framework called a rebar cage, over which the concrete columns are erected. After the
column goes up, the pre-fabricated pieces upon which the train travels can be assembled
and lifted into place.
The construction crew completes one column
cluster per day, and on some days two. The distance between columns is just over 150 feet.
This means that the pile driving phase, which is by far the most disruptive part of the
process, never takes place near the same block for more than one day.
"What you see is two years of planning
and experience of doing it on site at the airport. One of our biggest concerns is to move
quickly to get (past) each home quickly." said Quentin Brathwaite, Project Manager
for the Van Wyck portion of the construction.
The city Department of Transportation has
instituted a moratorium on all highway traffic during the holiday months and all
construction will be halted on Nov 11. Brathwaite estimates that the project will be clear
of homes as far north as Linden boulevard by then.
The Committee for Better
Transit, a civic group, has been opposed to the AirTrain plan from the beginning, and is
currently suing to have state funding for the project cut.
"The drilling is not only disruptive
but destructive" said George Haikalis. "The foundations of a number of homes
have been cracked by this project already."
According to the Port Authority, while
numerous complaints were made, the vast majority have been nuisance complaints, not claims
for damages. Of the damage claims, they say, were for sums ranging from $300 to $1,500.
"All substantiated claims were paid
through an amended system coordinated through our insurance company to expedite claims to
get the check into residents hands faster," said Brathwaite. "We are doing
everything that can be done to make the work along the expressway less intrusive."
Throughout construction,
vibration monitors are being installed on the service roads to ensure that vibration
levels are kept within the ranges established by the EPA. Additional monitors will be
placed on cross streets approximately 200 to 400 feet from the guide way, both east and
west. Pile-driving is by far the most disruptive portion of the process.
"To date, monitors have never exceeded
the EPAs acceptable decibel range," said Brathwaite. "However, in the
instances where complaints have been filed we have endeavored to settle them with all
haste."
Perhaps the strongest
criticism of the project is that the three-mile link from Kennedy to Jamaica has no stops
along the route. The light rail passes through a community that opponents say doesnt
want or need the train.
"It doesnt serve people locally.
says Haikalis" you can look at it but not use it.
"For all the digging and congestion
and noise," points out Haikalis "when this thing is done this neighborhood will
have a train built through its backyard that doesnt have a single stop in
Jamaica."
The argument did not fall on deaf ears.
The Transit Authority began a
beautification program at Rockaway Boulevard that includes a recreation center, as well as
the York College Aviation Institute.
"When the opinion was voiced to us
that the project did not directly benefit the community, we set in motion a set of
concessions to see that it benefits indirectly." Brathwaite said. "If you live
four minutes from the airport why would you take the train? You could take a cab."
Perhaps the strongest criticism of the
project is that it requires travelers to add yet another leg to their airport trek.
Haikalis said the shuttle bus that runs from the Howard Beach Station already performs the
same service at no cost.
"Most air travelers reject the idea of
transferring in the middle of their trip. More people will take the A because
who wants to pay five dollars for a free ride?"
While Brathwaite concedes that he points
out that the A train route doesnt serve everyone, and was itself criticized on its
completion for the same shortcoming.
"There are a lot of people in Queens
and Brooklyn who would rather pay $5 and make their flight than pay $35 and sit in
traffic. And the trains present conception doesnt preclude a future one-seat
ride at some point. But you have to have a train system first before you can have a
one-seat system."
Carlisle Towery, of the
Greater Jamaica Development Corporation sees the railway as a means to revitalize downtown
Jamaicas business district.
"Our hope is to make Jamaica a
destination," said Towery. "Our interest is to make Jamaica not just a place to
go through, but a place to go to."
The aviation industry is the boroughs
second largest employer. Forty-three percent of Kennedys employees are Queens
residents. Port Authority numbers indicate that approximately 7,000 people per day will
take the LIRR or MTA to the Air Train. In the end analysis, southeast Queens is to be a
part of the financial success of Kennedy Airports expansion.
"We expect another 13 million people
to use the Airport by 2010. If the Van Wyck is already gridlocked how are they going to
get there?"
For more information about the AirTrain, call the port
Authority hotline: 877-535-2478.; or visit their website at www.jfkairtrain.com. |